Check here before your next trip to see what’s underway at the airport and what’s ahead.
Project Description:
As the final phase of our comprehensive airport terminal rehabilitation, the newly completed Arrivals Hall will feature a redesigned car rental area, an expanded entry and exit vestibule, and seamless integration with the rest of the terminal to create a cohesive and welcoming experience. Inspired by the natural beauty of Saskatchewan, the space will reflect elements of the sun, the river, and the prairie grasses that define our region. This multi-phase project will last for approximately 18 months and result in periodic adjustments to traffic flow.
Start Date: June 2026
Estimated Completion Date: December 2027
What to expect during the current phase:
Project Description:
As part of life-cycle replacement, we will be replacing our 2 main escalators that connect our pre-board screening area to all departure gates.
Start Date: Fall 2025
Estimated Completion Date: Summer 2026
What to expect:
Project Description:
Located on the corner of Airport Drive and 45th Street, Tim Horton’s will cater to the friends and family coming to pick up or drop off travelling guests.
Start Date: Spring 2026
Estimated Completion Date: Winter 2027
What to expect:
Project Description:
Description: Final trenching and hook up to the building will complete the installation of our 1MW solar facility.
Start Date: June 2026
Estimated Completion Date: August 2026
What to expect:
What to expect: From the terminal or Highway 11 you may see some trenching equipment around the solar panels or around the airside property.
Project Description:
Description: Life-cycle rehabilitation work on Apron 5 and taxiway Charlie.
Start Date: Early June 2026
Estimated Completion Date: Early July 2026
What to expect:
What to expect: You may see construction equipment near the airside buildings along Avenue C or Highway 11.
Project Description:
Description: Rehabilitation of the service road to the terminal, known as Airport Road will be completed.
Start Date: Mid August 2026
Estimated Completion Date: End of August 2026
What to expect:
What to expect: Road detours will be in place at various phases of the project. Follow road signs.
Project Description:
Description: Located post-security in the terminal building, Tim Horton’s will be renovated to include an updated ambiance and self-serve ordering capabilities.
Start Date: September 2026
Estimated Completion Date: November 2026
What to expect:
During the renovation, a temporary coffee and snack kiosk will be available for travelling guests post-security.
Starbucks will also be open to serve the public during regular operating hours.
Project Description:
Description: A new micro market will provide an opportunity for guests to quickly pick up pre-made snacks.
Start Date: September 2026
Estimated Completion Date: November 2026
What to expect:
There will be a small horded off area next to the ReFuel restaurant seating area.
The ReFuel restaurant will remain open during regular operating hours.
Project Description:
Description: YXE is excited to announce that CATSA Plus, including CT X-ray technology, will be coming to YXE.
This innovation allows airports to integrate this advanced technology and enhance the passenger experience.
Investment in CATSA Plus lines have demonstrated shorter lines, when combined with CT X-rays, that can deliver higher throughput than traditional multi-view X-rays and roller tables.
Travellers being screened through lines with CT X-ray technology are not required to remove permitted liquids, aerosols, gels (less than 100 ml each), medical devices, or large electronics such as laptops from their carry-on baggage during screening.
Start Date: Fall 2026
Estimated Completion Date: Spring 2027
What to expect:
There will be minimal disturbances to the wait times during the construction period.