Good morning,
Please see below for the upcoming crack sealing work scheduled for Monday, July 6 through Thursday, July 9. These activities will require temporary closures and operational restrictions.
Monday, July 6
- Taxiway B south of Apron I closed: 1800–2100L
- Runway 15/33 closed: 2100–0500L
Tuesday, July 7
- Taxiway B north of Taxiway Alpha closed: 1800–2100L
- Runway 09/27: 30-minute PPR – airline operations only: 2100–0500L
- Taxiway F: 30-minute PPR: 2100–0500L
- Runway 15/33 closed: 0115–0415L (intersection work)
Wednesday, July 8
- Taxiway A West closed: 2100–0000L
- Taxiway A East closed: 0100–0400L
- Work will also be taking place on the hangar line and Taxiway C.
Thursday, July 9
- Work is planned on uncontrolled surfaces only. Should access to controlled surfaces become necessary, additional NOTAMs will be issued.